Greenwood Luxury Township

Premium gated community featuring 500 residential units across 45 acres. Includes 2/3/4 BHK apartments with world-class amenities, landscaped gardens, clubhouse with swimming pool, sustainable infrastructure, 100% power backup, water harvesting, and RERA certification.

Location

Sohna Road, Gurgaon

Client

Greenwood Developers Pvt Ltd

Year

2023

Case Study

Client industry: Real Estate Development

Challenge

Greenwood Developers required a premium 45-acre gated township on Sohna Road with 500 residential units, world-class amenities, RERA compliance, and sustainable infrastructure — all delivered within a 36-month timeline while managing 850+ workers and a ₹250 crore budget across multiple construction phases.

Solution

We adopted a phased master-plan approach starting with infrastructure development (roads, utilities, STP, water harvesting) in Year 1, followed by parallel tower construction across multiple blocks in Years 2-3. A dedicated RERA compliance team maintained escrow accounts and quarterly filings from day one. Our architectural team designed optimized 2/3/4 BHK layouts maximizing natural light and ventilation while integrating 100% power backup, rainwater harvesting, and landscaped community spaces.

Results

All 500 units delivered within the 36-month commitment with full RERA compliance and zero regulatory issues. The township achieved a 95% occupancy rate within 6 months of handover. Sustainable features reduced common area energy costs by 35%, and the community's water recycling system saves approximately 50,000 liters per day. The project managed 850 workers at peak with an exemplary safety record.

Project Statistics

Total Area

0

acres

Duration

0

months

Budget

₹0

Project Value

Workforce

0

Workers

Project Gallery

3 images

Click any image to view in full screen. Use arrow keys to navigate.

From Vacant Land to Thriving Community

Before
After
Before
After
Drag the slider to compare

Project Timeline

Master Planning & Approvals

Completed
Jan 2020 - Jun 2020

Site planning, architectural designs, and regulatory approvals

Infrastructure Development

Completed
Jul 2020 - Jun 2021

Roads, utilities, and common area development

Tower Construction

Completed
Jul 2021 - Mar 2023

Construction of residential towers and amenities

Landscaping & Handover

Completed
Apr 2023 - Sept 2023

Final landscaping and unit handover to residents

Completed